Project Specification
- Client: Citigroup
- Products: o8 air
- Project Scope: 387 Positions
- Location: London, Dubai, Moscow and Schiphol
- Completion: 2006-2012
Summary
DAS first installed for Citibank in Moscow in 2006 by supplying 46 Optima 5 desks. The following year, 2007, DAS were appointed to provide 24 Optima 5 trading desks for Citibank Dubai.
In 2011 DAS were chosen in open competition to manufacture, deliver and install 312 o8 air, electrically height adjustable trading desks at their Citigroup centre 1 in Canary Wharf, London.
DAS had an exceptionally tight deadline to install the o8 air desks at Canary Wharf but successfully completed installation in under 5 weeks from order to completion. In addition, the project requirements included the retro-fitting of the associated heat exchange units for 30% of the installed desks.
Following these three successful projects, in 2012 DAS installed o8 electronically height adjustable desks at Citibank Schiphol to match the current desks in London.